docs(state): record phase 7 context session
This commit is contained in:
+11
-11
@@ -2,16 +2,16 @@
|
|||||||
gsd_state_version: 1.0
|
gsd_state_version: 1.0
|
||||||
milestone: v1.0
|
milestone: v1.0
|
||||||
milestone_name: milestone
|
milestone_name: milestone
|
||||||
status: complete
|
status: completed
|
||||||
stopped_at: all phases complete
|
stopped_at: Phase 7 context gathered
|
||||||
last_updated: "2026-06-25T12:00:00.000Z"
|
last_updated: "2026-06-26T12:22:38.551Z"
|
||||||
last_activity: 2026-06-25 -- Phase 06 all plans complete
|
last_activity: 2026-06-25 -- Phase 06 complete (CI green, AppImage built)
|
||||||
progress:
|
progress:
|
||||||
total_phases: 6
|
total_phases: 7
|
||||||
completed_phases: 6
|
completed_phases: 5
|
||||||
total_plans: 24
|
total_plans: 24
|
||||||
completed_plans: 24
|
completed_plans: 23
|
||||||
percent: 100
|
percent: 71
|
||||||
---
|
---
|
||||||
|
|
||||||
# Project State
|
# Project State
|
||||||
@@ -115,6 +115,6 @@ Items acknowledged and carried forward from previous milestone close:
|
|||||||
|
|
||||||
## Session Continuity
|
## Session Continuity
|
||||||
|
|
||||||
Last session: 2026-06-25T12:00:00Z
|
Last session: 2026-06-26T12:22:38.543Z
|
||||||
Stopped at: All 6 phases complete — v1.0 milestone done
|
Stopped at: Phase 7 context gathered
|
||||||
Resume file: None
|
Resume file: .planning/phases/07-dkv-fleet-module/07-CONTEXT.md
|
||||||
|
|||||||
Reference in New Issue
Block a user