docs(10-03): complete DÖE source adapter & normalizer plan

This commit is contained in:
2026-07-21 11:01:50 +02:00
parent 31607df48c
commit 761077814f
4 changed files with 196 additions and 9 deletions
+9 -4
View File
@@ -6,14 +6,14 @@ current_phase: 10
current_phase_name: ausschreibungs-radar-foundation-d-e-ingestion
status: executing
stopped_at: Completed 10-02-PLAN.md
last_updated: "2026-07-21T08:46:07.001Z"
last_updated: "2026-07-21T09:01:03.926Z"
last_activity: 2026-07-21
last_activity_desc: Phase 10 execution started
progress:
total_phases: 14
completed_phases: 8
total_plans: 46
completed_plans: 41
completed_plans: 42
percent: 57
---
@@ -29,7 +29,7 @@ See: .planning/PROJECT.md (updated 2026-07-17)
## Current Position
Phase: 10 (ausschreibungs-radar-foundation-d-e-ingestion) — EXECUTING
Plan: 3 of 6
Plan: 4 of 6
Status: Ready to execute
Last activity: 2026-07-21 — Phase 10 execution started
@@ -73,6 +73,7 @@ Progress: [░░░░░░░░░░] 0%
| Phase 09 P06 | 7 | 3 tasks | 7 files |
| Phase 10 P01 | 15min | 3 tasks | 4 files |
| Phase 10 P02 | 20min | 3 tasks | 6 files |
| Phase 10 P03 | 35min | 3 tasks | 9 files |
## Accumulated Context
@@ -144,6 +145,10 @@ Recent decisions affecting current work:
- [Phase 10-02]: category: 'procurement' fuer Ausschreibungs-Radar im Marketplace gewaehlt (freies kebab-case, keine Enum-Beschraenkung)
- [Phase 10-02]: Singleton doe-opendata Poll-Config wird direkt in TendersModule.onModuleInit() upserted, isActive:true per Default (D-04)
- [Phase 10-02]: Platzhalter-Seite tender-radar/page.tsx nutzt hartkodierten deutschen Text statt next-intl (volle i18n ist CONFIG-03, Phase 14)
- [Phase 10-03]: Real DÖE fixtures live-captured (pubDay=2026-07-19), not synthetic — 8 notices spanning all D-02 tag classes
- [Phase 10-03]: sourceNoticeId = OCDS release.id (stable, no version suffix), not the zip entry filename
- [Phase 10-03]: eForms-DE XML primary for deadlineAt/estimatedValue/procedureType; OCDS primary for ocid/buyerName/title/cpvCodes/region/plz
- [Phase 10-03]: bundesland left null this plan — NUTS-to-Bundesland mapping deferred to Phase 11 filter UI
### Pending Todos
@@ -181,7 +186,7 @@ Items acknowledged and carried forward from previous milestone close:
## Session Continuity
Last session: 2026-07-21T08:46:06.990Z
Last session: 2026-07-21T09:00:23.857Z
Stopped at: Completed 10-02-PLAN.md
Resume file: None
Last activity: 2026-07-14 - Built LDAP per-user exclude/denylist filter (9d1323f), migration applied on live DB, verified via Playwright: sync deactivated 4 excluded service accounts (administrator/krbtgt/guest/dns-ldap), 2 real LDAP users stay active, 0 wrongly created