docs(05-01): complete dashboard grid + clock widget plan

This commit is contained in:
2026-06-24 11:27:59 +02:00
parent 8a9c1ae6a9
commit afc555b18d
4 changed files with 159 additions and 23 deletions
+15 -13
View File
@@ -2,15 +2,15 @@
gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
status: completed
stopped_at: context exhaustion at 76% (2026-06-24)
last_updated: "2026-06-24T08:12:35.458Z"
last_activity: 2026-06-23 -- Plan 04-03 completed (sidebar enhancement)
status: executing
stopped_at: Completed 05-01-PLAN.md
last_updated: "2026-06-24T09:27:38.939Z"
last_activity: 2026-06-24 -- Phase 05 execution started
progress:
total_phases: 6
completed_phases: 3
total_plans: 21
completed_plans: 15
completed_plans: 16
percent: 50
---
@@ -21,14 +21,14 @@ progress:
See: .planning/PROJECT.md (updated 2026-06-18)
**Core value:** Eine zentrale Plattform, in der beliebige Workflow-Tools als Module lizenziert, aktiviert und genutzt werden koennen -- ohne zwischen verschiedenen Anwendungen wechseln zu muessen.
**Current focus:** Phase 04 — marketplace-portal-navigation
**Current focus:** Phase 05 — dashboard-calendar
## Current Position
Phase: 04 (marketplace-portal-navigation) — EXECUTING
Plan: 4 of 4
Status: Plan 04-03 complete, ready for 04-04
Last activity: 2026-06-23 -- Plan 04-03 completed (sidebar enhancement)
Phase: 05 (dashboard-calendar) — EXECUTING
Plan: 2 of 5
Status: Ready to execute
Last activity: 2026-06-24 -- Phase 05 execution started
Progress: [██▓░░░░░░░] 25%
@@ -54,6 +54,7 @@ Progress: [██▓░░░░░░░] 25%
*Updated after each plan completion*
| Phase 02-authentication-multi-tenancy P02 | 8min | 3 tasks | 26 files |
| Phase 02-authentication-multi-tenancy P03 | 5min | 2 tasks | 20 files |
| Phase 05-dashboard-calendar P01 | 14min | 4 tasks | 28 files |
## Accumulated Context
@@ -74,6 +75,7 @@ Recent decisions affecting current work:
- [Phase ?]: Route groups (auth)/(portal) for layout separation: auth pages standalone, portal pages wrapped in AppShell
- [Phase ?]: Controller-level tenant isolation for ADMIN role as defense-in-depth alongside RLS
- [Phase ?]: Remember-me controls cookie maxAge (30d session vs browser-session) not separate token type
- [Phase ?]: react-grid-layout v2 uses dragConfig/resizeConfig instead of isDraggable/isResizable
### Pending Todos
@@ -93,6 +95,6 @@ Items acknowledged and carried forward from previous milestone close:
## Session Continuity
Last session: 2026-06-24T08:03:21.832Z
Stopped at: context exhaustion at 76% (2026-06-24)
Resume file: .planning/phases/05-dashboard-calendar/05-CONTEXT.md
Last session: 2026-06-24T09:27:38.933Z
Stopped at: Completed 05-01-PLAN.md