docs(07-02): complete DKV inbox-access layer plan
- 07-02-SUMMARY.md: interface + IMAP + Exchange providers, all 3 DTOs, self-check passed - STATE.md: advance to Plan 3/6, record 3 decisions, update session to 2026-06-27 - ROADMAP.md: mark 07-01 and 07-02 complete, Phase 7 progress 2/6
This commit is contained in:
+12
-9
@@ -3,9 +3,9 @@ gsd_state_version: 1.0
|
||||
milestone: v1.0
|
||||
milestone_name: milestone
|
||||
status: executing
|
||||
stopped_at: Phase 07 Plan 01 complete
|
||||
last_updated: "2026-06-26T17:36:00.000Z"
|
||||
last_activity: 2026-06-26 -- Phase 07 Plan 01 completed (DKV backend foundation)
|
||||
stopped_at: Phase 07 Plan 02 complete
|
||||
last_updated: "2026-06-27T00:10:00.000Z"
|
||||
last_activity: 2026-06-27 -- Phase 07 Plan 02 completed (DKV inbox-access layer)
|
||||
progress:
|
||||
total_phases: 7
|
||||
completed_phases: 5
|
||||
@@ -26,9 +26,9 @@ See: .planning/PROJECT.md (updated 2026-06-18)
|
||||
## Current Position
|
||||
|
||||
Phase: 07 (dkv-fleet-module) — EXECUTING
|
||||
Plan: 2 of 6
|
||||
Status: Executing Phase 07 (Plan 01 complete)
|
||||
Last activity: 2026-06-26 -- Phase 07 Plan 01 completed (DKV backend foundation)
|
||||
Plan: 3 of 6
|
||||
Status: Executing Phase 07 (Plan 02 complete)
|
||||
Last activity: 2026-06-27 -- Phase 07 Plan 02 completed (DKV inbox-access layer)
|
||||
|
||||
Progress: [██████████] 100%
|
||||
|
||||
@@ -99,6 +99,9 @@ Recent decisions affecting current work:
|
||||
- [07-01]: DKV PDF uses two extraction formats: single-tx (tab-separated) vs multi-tx (columnar) — both handled in DkvParserService
|
||||
- [07-01]: Research Pattern 4 regex replaced with empirical dual-format tab/columnar parser after testing against real invoice.pdf
|
||||
- [07-01]: CalendarCryptoService exported from CalendarModule for DKV credential encryption reuse
|
||||
- [07-02]: Max attachment size 25MB enforced in both ImapProvider and ExchangeInboxProvider before buffering (T-07-05)
|
||||
- [07-02]: ExchangeInboxProvider uses WellKnownFolderName.Inbox + FindItems (not FindAppointments — email vs calendar EWS API)
|
||||
- [07-02]: export type {} required for type-only re-exports under isolatedModules TypeScript setting
|
||||
|
||||
### Pending Todos
|
||||
|
||||
@@ -118,6 +121,6 @@ Items acknowledged and carried forward from previous milestone close:
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-06-26T17:36:00.000Z
|
||||
Stopped at: Phase 07 Plan 01 complete (DKV backend foundation)
|
||||
Resume file: .planning/phases/07-dkv-fleet-module/07-02-PLAN.md
|
||||
Last session: 2026-06-27T00:10:00.000Z
|
||||
Stopped at: Phase 07 Plan 02 complete (DKV inbox-access layer)
|
||||
Resume file: .planning/phases/07-dkv-fleet-module/07-03-PLAN.md
|
||||
|
||||
Reference in New Issue