- SUMMARY.md documenting design tokens, i18n, layout components - STATE.md advanced to plan 2/3, decisions recorded - ROADMAP.md updated to 2/3 plans complete - REQUIREMENTS.md: PRTAL-01, PRTAL-04, UI-01, UI-02, UI-03 marked complete
2.7 KiB
gsd_state_version, milestone, milestone_name, status, stopped_at, last_updated, last_activity, progress
| gsd_state_version | milestone | milestone_name | status | stopped_at | last_updated | last_activity | progress | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.0 | v1.0 | milestone | executing | Completed 01-02-PLAN.md (Portal Shell) | 2026-06-18T08:28:41Z | 2026-06-18 -- Plan 01-02 Portal Shell complete |
|
Project State
Project Reference
See: .planning/PROJECT.md (updated 2026-06-18)
Core value: Eine zentrale Plattform, in der beliebige Workflow-Tools als Module lizenziert, aktiviert und genutzt werden koennen -- ohne zwischen verschiedenen Anwendungen wechseln zu muessen. Current focus: Phase 1 - Foundation & Portal Shell
Current Position
Phase: 1 of 6 (Foundation & Portal Shell) Plan: 2 of 3 in current phase (completed) Status: Executing phase 1 Last activity: 2026-06-18 -- Plan 01-02 Portal Shell complete
Progress: [██░░░░░░░░] 10%
Performance Metrics
Velocity:
- Total plans completed: 2
- Average duration: 12 min
- Total execution time: 0.38 hours
By Phase:
| Phase | Plans | Total | Avg/Plan |
|---|---|---|---|
| 01-foundation-portal-shell | 2/3 | 23 min | 12 min |
Recent Trend:
- Last 5 plans: 01-01 (16 min), 01-02 (7 min)
- Trend: improving
Updated after each plan completion
Accumulated Context
Decisions
Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:
- [Roadmap]: 6 phases derived from 44 v1 requirements, standard granularity
- [Roadmap]: Research recommends NestJS + Next.js + PostgreSQL RLS + Keycloak + Tauri stack
- [01-01]: Used Traefik v2.11 instead of v3.4 due to Docker API version incompatibility on host
- [01-01]: Traefik placed on frontend-net + backend-net for routing to both web and api services
- [01-01]: API Dockerfile copies full monorepo node_modules structure for pnpm workspace compatibility
- [01-02]: OKLCH color space for all design tokens (Tailwind v4 native, perceptually uniform)
- [01-02]: Dark mode uses oklch(0.17 0.01 260) dark gray-blue for comfortable contrast with yellow primary
- [01-02]: Cookie-based locale (NEXT_LOCALE) instead of URL routing for portal app
- [01-02]: CSS custom property --current-sidebar-width for responsive main content margin
Pending Todos
None yet.
Blockers/Concerns
None yet.
Deferred Items
Items acknowledged and carried forward from previous milestone close:
| Category | Item | Status | Deferred At |
|---|---|---|---|
| (none) |
Session Continuity
Last session: 2026-06-18T08:28:41Z Stopped at: Completed 01-02-PLAN.md (Portal Shell) Resume file: .planning/phases/01-foundation-portal-shell/01-03-PLAN.md